Ryan Latta

Hiya,

Estimation is one of those things that never seems to go well but everyone keeps repeating. There's a lot in this topic to get into, but I'll try to give a few little pointers that might help.

1) Have everyone estimate secretly and take the average. Group averages tend to be far better than individuals unless they are a provable "Expert." Try it out one day by bringing in a book nobody is familiar with and have them estimate the number of pages this way.

2) Since you know initial and actuals you can take sample the past 10-20 and create an average that you're off by that the PM can use to pad your estimates.

3) Estimate using ranges. Instead of it being 6 hours, its 6 hours - 3 days. The low is everything going right, the high you want to feel 85% confident in. Wanna figure out how confident you are? How much money are you willing to bet on your range?

4) Drop this BS entirely and ask your PM to start using Monte Carlo simulations to Forecast instead of adding estimates.

5) Right-size work instead of estimating. There is probably a size of work that you all are close to right on. Lots of groups I work with that tends to be a day. Break your work down to that size instead of estimating.

6) You could attempt to use Story Points instead of time, but that usually doesn't work out too much better because someone will try to compare points to time and you'll be in the same boat.

I realize these are short statements, but each are ones I've employed at various clients to help with the stress of estimating.

Collapse
 
isaactorresmichel profile image
Isaac Torres Michel

I can totally relate to your last point. We moved from time-estimation to story points, but.... we're still estimating doing conversion of points-time values.

Collapse
 
recursivefaults profile image
Ryan Latta

You can also get a little nasty about it and ask the PMs to estimate the ROI, customer satisfaction, or opportunity cost while reminding them that you need them to estimate as accurately as possible since they need to hit their business objectives.

I've done that one before too, a bit bold, but usually helps people realize that certainty in estimates doesn't exactly work, but feedback and prioritization do.