On 23rd of September, I had a weekly meeting with regards to my Google's Season Of Docs project. The mentor's had assigned the following tasks :
- Finish reading the Plugins Docs and include Plugins doc into the main docs.
- Sending the Google doc containing relevant info from ACS research paper.
- Solving the Table of contents issue.
- Completing the implementation of API using the UI of SynBioHub.
- Completing the setup page.
- Include the link of the plugins table rather than the whole table on the plugins page.
I was able to accomplish the following tasks:
- Extracted out relevant info from the ACS research paper, though it was too much. Hence, on the advise of Prof. Myers I'm trying to reduce the content to 1 paragraph at max containing info. about Plugins ans Web-Of-Registries.
- Solved the table of contents issues, thanks to My mentor and developer of ACE-documentation theme.
- Included the link of plugins table in the documentation that has already been implemented, hence removing the whole table from the docs, which was not looking up to the mark.
- I'm almost done including the Plugins doc into the Plugins section of the documentation. A little bit of formatting and editing is left to be done.
- I was able to execute almost all the API's using the UI of SynBioHub.
Following are the issues that I'd faced this week:
- Extracted out too much of information from the ACS research paper, hence on the advice of Prof. Myers, I've substantially reduced the content and plan to reduce it further.
- I haven't used Sendgrid before, hence it was kind of a challenge for me to learn about it's nuances, but still I was able to complete the Setup page well on time.
- I'm still encountering some challenges on running locally onto Ubuntu. Hence, I tried to run it on a Mac, on which it successfully ran without any glitches. I tried to do a bit of research, according to which I need to install docker again onto my PC.
- The doc that Jet had sent contained a lot of information on plugins. I do have some doubts and I'll try to clarify them in the meeting.
I was able to complete almost all the tasks, this week well in time. Hope to discuss the upcoming tasks in the next meeting i.e. on 30th September!